North 24th St Streetscape Improvements
The purpose of this project is to enhance the safety, accessibility, and aesthetics of North 24th Street from Ohio Street to Sahler Street.
Project Features
Improvements
- Pedestrian nodes to shorten crossing distances
- On street parallel parking
- Sidewalks and ADA curb ramps
- Landscaping
- Signage
- Pedestrian-scale lighting
- Possible traffic calming
- Possible sewer modifications
Schedule
- Design Notice to Proceed: February 2025
- Preliminary Design Submittal: May 2025
- Right-of-Way (if necessary): January 2026 to July 2026
- Final Design Submittal: April 2026
- Bid for Construction: August 2026
- Construction Begins: Spring 2027
Status Updates
March 9, 2026
General Project Management
-
City presented project updates at BID’s 2026 Partners Meeting on 2/23/26. The next Partners Meeting is scheduled for 10/26/26.
-
The City’s subconsultant, Wilson & Co., is finalizing conceptual designs of roundabout projects at Binney, Sprague, and Hamilton. These potential future projects are not included in the current project due to the funding limitations.
-
City received Notice to Proceed with Right-of-Way (ROW) process on 12/29/25. The remaining tentative ROW schedule is as follows:
- 1/26/26 - 4/03/26 Primary appraisals (50 working days)
- 4/06/26 - 5/01/26 Review appraisals (20 working days)
- 5/04/26 - 5/15/26 NDOT review (2 weeks)
- 6/01/26 Make offers and begin negotiations
- 7/20/26 Start condemnation proceedings if necessary (no later than)
Design (PE) Status
- Confluence joined the design team as a subconsultant to Schemmer to provide master plan conformance review and landscaping design.
- Received notice to proceed (NTP) on 2/3/2026.
- Responsible for the North 24th St. Streetscape Master Plan in 2020-2021 (https://confluence.mysocialpinpoint.com/north24)
- Schemmer and Confluence are coordinating design as they await environmental (NEPA) approval and NTP for final design.
- Schemmer continues to work with City ROW Division during appraisal process.
Environmental (NEPA) Status
- HDR is completing final updates to the Categorical Exclusion (CE) document and intends to submit to NDOT on 3/9/26 and route for final signatures and NEPA approval within the week.
Upcoming Milestones
- March 30, 2026 - Submittal of 90% plans to NDOT and Urban Design Review Board
Document Library
Design Plans, Studies & Reports
Community Engagement
February 2026 North 24th St BID Partners Meeting
October 2025 North 24th St. BID Stakeholder Meeting
February 2025 North 24th St BID Stakeholder Meeting
January 2024 North 24th St BID Stakeholder Meeting
- Presentation
- Original Concept