Construction Updates
November 22, 2022
Construction on the I Street project will temporarily shut down for the winter months by the end of the day Saturday, November 26, 2022. With the winter shut down, I Street from 108th to 102nd streets will reopen to all traffic at that time. Utility relocation and storm sewer work along the project corridor over the winter months is anticipated within the city’s right-of-way.
For more information:
September 19, 2022
The first phase of work on the City of Omaha’s I Street project between 108th Street and the Interstate 80 (I-80) ramp is nearing completion, and crews are tentatively scheduled to reopen traffic in late September. The project has progressed ahead of schedule, and therefore construction of Phase 2 is also scheduled to begin in late September. The contractor, Charles Vrana & Son Construction Company, will being construction of Phase 2 on Monday, September 26, 2022. Please see the construction phasing details and maps below for reference.
Crews will begin with Phase 2A on I Street from 108th to 102nd streets. During this construction, a full closure of I Street will be in place from 108th east for approximately 700 feet.
For more information:
August 15, 2022
Vrana continues to make progress along the corridor, moving into the next phase of work starting Monday, August 22, 2022. Please see attached for details on turning restrictions at 108th and I streets as part of this work.
For more information:
July 7, 2022
Starting next Wednesday, July 13, 2022 work will begin on the west half of the 108th Street intersection. North and southbound traffic will be maintained on 108th Street under two-way head-to-head traffic and temporary traffic control shifting southbound traffic to the east half of the intersection.
For more information:
June 16, 2022
Starting tomorrow (Friday, June 17, 2022), roadway work on the south side of I Street from the I-80 ramp will progress to 110
th Street and roadway removals will begin at the 110
th and I Street intersection. Click
here for more information.
May 2022
The City of Omaha’s “I” Street project between 108th Street and the Interstate 80 (I-80) ramp, is scheduled to begin on Tuesday, May 10, 2022. Utility relocation work has begun and will continue throughout the project corridor for the remainder of the 2022 construction season into 2023. Utility agencies will coordinate with properties as needed during their operations. The contractor, Charles Vrana & Son Construction Company, plans to begin construction with a full closure of “I” Street from 108th Street to the I-80 ramp beginning May 10, 2022.
For more information: