Cuming St, NW Radial Hwy, Military Ave Corridor Study
The purpose of this project is to improve safety for all users, walkability, and multi-modal opportunities along the Nebraska Highway 64 / Link Highway 28-K corridor of Cuming Street (28th Street to Northwest Radial Highway), Northwest Radial Highway (Cuming Street to Military Avenue/ 63rd Street), and Military Avenue (Northwest Radial Highway/ 63rd Street to 70th Avenue).
Project Features
Improvements
- The project will include a study to develop a plan for improvements on the corridor to improve safety and access for all users and identify opportunities to improve multi-modal usage.
Schedule
- Data Collection: August/ September 2024
- Existing Conditions Analysis: September/ October 2024
- Initial Public Outreach: November/ December 2024
- Alternatives Development and Analysis: January-May 2025
- Final Public Outreach: June 2025
- Draft Study Report: July 2025
- Final Study Report: September 2025
Document Library
Reports & Studies
Community Engagement
Contact the Project Team
Project Contacts
Nicholas Gordon, P.E., PTOE, RSP1
Project Manager, Public Works
402-444-5220