The existing 4-lane section of Crown Point Avenue between 72nd Street and Blair High Road has reached the end of its useful life. This project will construct new pavement and install ADA compliant ramps and sidewalks meeting current standards.

The City of Omaha has hired Olsson Associates to provide ​p​rofessional ​e​ngineering services for the reconstruction of Crown Point Avenue from 72nd Street to Blair High Road.  Olsson Associates will complete an analysis to determine the most appropriate cross section for the reconstructed road.

Project Schedule

Project Schedule.JPG

Announcement

 
During construction of Crown Point Avenue access to Northwest High School will consist of the following:
  • The traffic pattern to access Northwest High School will consist of a one-way travel pattern.
  • Vehicles and buses will enter Northwest High School from Vernon Avenue.
  • Vehicle drop off and pick up will take place on the west side of the school.
  • Bus drop off and pick up will take place on the east side of the school.
  • Vehicles and buses will exit the school utilizing their respective driveways.
 
NW High Traffic Pattern Map.JPG

Construction Updates

 
October 7, 2020
Effective Thursday, October 8, 2020, the intersection of 78th St and Crown Point Ave will be closed for construction for approximately 7 weeks.
 
September 11, 2020
  • Crown Point Avenue from Blair High Road to Wenninghoff Road is open to traffic.
  • Crown Point Avenue from Blair High Road to the east entrance of Northwest High School is open to local traffic ONLY.
  • Crown Point Avenue east of the east entrance of Northwest High School to 78th Street is closed with exception to homeowner traffic only.
 
 February 24, 2020
  • Effective Monday, February 24, 2020, the intersection of Crown Point Ave and Wenninghoff Road will be closed for reconstruction. (See attached)
  • Access to businesses along the west side of Wenninghoff Road is available from Vernon Avenue or from southbound Wenninghoff Road.

Notice of Informational Meeting

 

See below for information from a public information meeting held Tuesday, January 21, 2020. 
 
 
See below for information from a public information meeting held Wednesday, February 13, 2019. 
 
Roundabout reference material:
 
Please see the link below for a copy of the Open House Announcement Letter, Meeting Handout, Comment Forms, Presentation and Alternates with details:
 
 
Please see the link below for a copy of the letter sent to residents May 30th, 2018 regarding the project:
 

Crown Point Improvement Project Letter to Adjacent Property Owners

 Contact Us

  • To submit a comment or receive project updates, join the project mailing list through our contact form.
  • To provide your input about a specific location within the project area, visit the City Map.

 Queries

City of Omaha Contact:
Troy Staroscik
Project Manager
City of Omaha
402-444-5220
Troy.Staroscik@cityofomaha.org