Project Update | August 28, 2024
Beginning Thursday, September 5, only right turns will be allowed entering and exiting Patterson Drive from 168th Street. The restriction will be in place for 3 weeks to allow the contractor to complete paving in the median areas of 168th Street.
168th Street West Center Road to Q St
The existing two-lane roadway is at capacity and often experiences delays during the peak hours. Improving safety for all transportation users, enhancing traffic operations, decreasing peak hour congestion, and improving drainage control are the primary benefits of the project.
Project Features
Improvements
- increase from two to four lanes with center median
- new roadway with curb and gutter
- enclosed storm sewer
- sidewalks
- retaining walls
- noise walls
- bridge over Zorinsky Lake
- traffic signals
Schedule
- Preliminary Design Work: 2007-2017
-
Noise, Traffic, Geotechnical, and Environmental Analyses
-
Preliminary Design
-
- Final Design Activities: 2018-2022
-
Additional Field Exploration
-
Final Design
-
Right-of-Way Acquisition
-
Letting and Bidding
-
- Construction: 2023-2024
-
Utility Relocation
-
Construction Preparation
-
Construction Begins
-
Document Library
Reports & Studies
Environmental Assessment 2017
Community Engagement
March 2023 Pre-Construction Meeting
May 2017 Public Hearing
Contact the Project Team
Project Contacts
Troy Staroscik
Project Manager, Public Works