144th Street Improvements - South and West Farm Development

About the Project

As part of the 144th Street Improvements and the West Farm and South Farm Development efforts, roadway improvements will be made on 144th Street, Pacific Street, and the off ramps to West Dodge Road.

144th Street has been widened from a 4-lane divided roadway to a 6-lane divided roadway from FNB Parkway/Eldorado Drive south to Pine Street. The 144th and Dodge interchange off ramps have been widened to add dual right turns, and Pacific Street has been reconstructed to allow for dual left turns into both West and South Farm developments.

Additionally, there will be some miscellaneous median work to allow for new entrances along 144th Street and Pacific Street into West Farm and South Farm and new traffic signals will be installed along the corridor.

click on image to enlarge

Project Updates

 
September 29, 2020
Beginning Thursday, October 1, 2020 at 9:00 pm continuing through Friday, October 2nd 5:00 am. eastbound West Dodge Road will have the left lane closed at 144th Street for work on the new signal truss by Commonwealth Electric.
 
January 10, 2020
On Monday, January 13, 2020, eastbound West Dodge Road will have a single lane closure and the off-ramp at 150th Street will be fully closed from 9:00 AM until 3:00 PM. Lanes will be closed to take core samples from the new pavement as part of the project closeout process.
 
November 21, 2019
Beginning Friday, November 22, 2019 at 9:00 pm and continuing through Saturday, November 23, 2019 at 7:00 am. 144th Street will be closed at W. Dodge Road for installation of traffic signal truss structure by Commonwealth Electric.
  • South Bound traffic will be forced to the West Bound W. Dodge Road on ramp.
  • North Bound traffic will be forced to the East Bound W. Dodge Road on ramp.
  • East Bound off ramp will be forced to South Bound 144th Street.
  • West Bound off ramp will be forced to North Bound 144th Street.
November 20, 2019
Due to rain in the weather forecast today, this project has been pushed back to begin Thursday, November 21, 2019 continuing through Friday, November 22, 2019 5:00am, east bound W. Dodge Road at 144th Street will have median lane closure between 8:00 pm-5:00 AM. This lane closure is required for Commonwealth Construction to perform bridge construction work for a new traffic signal truss structure.
 
November 18, 2019

Beginning Wednesday, November 20, 2019 continuing through Thursday, November 21 2019, east bound W. Dodge Road at 144th Street will have median lane closure between 8:00 pm-5:00 AM. This lane closure is required for Commonwealth Construction to perform bridge construction work for a new traffic signal truss structure.

August 30, 2019

All major construction activities have been complete. We are now in the process of replacing the temporary signals with the permanent signals at the intersections of 144th Street and Pine, Dewey, Nathan, and Pacific Street at Applied Boulevard and 153rd Street. The intent will be to complete the permanent signal pole installation during fall 2019. A new signal truss at 144th Street and West Dodge Road will be installed late 2019.

 Contact Us

To submit a comment or receive project updates, join the project mailing list through our contact form.

To provide your input about a specific location within the project area, visit the City Map.

 Queries

Victor Baez
Noddle Companies
402-496-1616
victor@noddlecompanies.com

City of Omaha Seal.png        NoddleLogo.png