Powered by Google TranslateTranslate
 
Powered by Google TranslateTranslate
 
Powered by Google TranslateTranslate
 
Powered by Google TranslateTranslate

180th Street - N. HWS Cleveland Boulevard to West Maple Road (Douglas County Project) (COMPLETED)

About the Project

North 180th Street between West Dodge Road and West Maple Road will be reconstructed to a four-lane roadway divided by a median. Currently, 180th Street does not connect between Old Lincoln Highway and Blondo Street, and is a 2-lane rural section between Blondo Street and West Maple Road. North 180th Street will be widened to a 4-lane roadway divided by a median between West Dodge Road and West Maple Road, then continuing north from West Maple Road and transitioning back to a two-lane roadway with a center turn lane at the north terminus of this near George Miller Parkway. These improvements will include new bridge structures crossing Old Lincoln Highway, the Union Pacific Railroad, and the West Papillion Creek as well as Whispering Ridge Creek. The roadway will have curb and gutter along both roadway edges with enclosed storm sewer. A ten-foot-wide trail will be constructed behind the east curb of the roadway, with a five-foot-wide sidewalk behind the west curb.

Blondo Street is currently a two-lane rural section throughout the project limits. This project will widen Blondo to a 4-lane roadway divided by a median for approximately 1000 feet on either side of the intersection with 180th Street. This roadway will taper back to match the existing roadway at the project limits at 183rd Street on the west and 176th Avenue on the east. A new bridge structure will carry Blondo Street over Whispering Ridge Creek just east of the existing intersection with 180th Street. Five-foot-wide sidewalks will be constructed behind curb on both sides of the improved section of Blondo Street.

The intersection of Blondo Street and 180th Street will be constructed with left and right turn lanes on all four approaches and will be controlled with a newly constructed traffic signal. The intersection of 180th Street and West Maple Road will be improved to allow left and right turn lanes at all four approaches and will be controlled by a newly constructed traffic signal.

Phase 1

Click to enlarge Phase 1 map

Phase 2

Click to enlarge Phase 2 map

Project Schedule

Anticipated Project Schedule:

Spring 2020: The contractor will begin site work with tree clearing and will begin to build embankments as well as the new viaduct structures between N HWS Cleveland and Blondo Street. Old Lincoln Highway will remain closed at this time, and construction traffic will be entering and leaving the jobsite via 180th Street and Blondo Street. 

Summer 2020: Beginning in late Spring 2020, the contractor will close Blondo Street from 176th Avenue and 183rd Street to allow reconstruction of Blondo Street, the bridge crossing Whispering Ridge Creek, and the intersection with 180th Street.  Work will continue between N HWS Cleveland and Blondo Street, which will require that Old Lincoln Highway remain closed. 180th Street will remain open from just north of Blondo Street to West Maple Road. (updated May 11, 2020)

Fall 2021: Work will conclude on the reconstruction of Blondo Street, 180th Street south of Blondo, and the bridge structures carrying 180th Street over Old Lincoln Highway, the Union Pacific Railroad, and West Papillion Creek. Blondo Street throughout the project and 180th Street from West Dodge to Blondo will be opened to traffic.  Old Lincoln Highway will return to its seasonal use schedule. 

The contractor will move northward to complete 180th Street from Blondo to the north end of the project as well as reconstructing the bridge crossing Whispering Ridge Creek. 180th Street will be closed from Blondo to West Maple, and from West Maple to the northern terminus of the project at George Miller Parkway. West Maple Road will remain open throughout the project, however there will be temporary lane closures to allow for widening and median construction during this phase.

Winter 2022: Contractor completes reconstruction of 180th Street north of Blondo, and opens all lanes to traffic.

Construction Updates:

November 11, 2022
Beginning Monday, June 27, 2022, 180th Street between West Maple Road and George Miller Parkway will be closed to traffic for approximately 45 days.  This will enable to the contractor to remove the existing roadway, grade for the new alignment, complete storm sewer and structures, install new traffic signals, and pave the new roadway.  This section of 180th Street will be re-opened to traffic prior to the beginning of fall classes at Elkhorn North High School on August 16.  The posted detour for this extended closure of 180th Street will utilize Blondo Street, 192nd Street, and Fort Street.
 
August 9, 2022
On Tuesday afternoon, August 9, the contractor will reopen 180th Street to traffic between West Maple Road and George Miller Parkway.  180th Street between West Maple Road and Blondo Street will remain closed while the contractor completes work in that area, with completion anticipated later in the Fall of 2022.  Please remain mindful of all posted signing, traffic signals, and construction traffic entering and leaving the site.
 
June 21, 2022
Beginning Monday, June 27, 2022, 180th Street between West Maple Road and George Miller Parkway will be closed to traffic for approximately 45 days.  This will enable to the contractor to remove the existing roadway, grade for the new alignment, complete storm sewer and structures, install new traffic signals, and pave the new roadway.  This section of 180th Street will be re-opened to traffic prior to the beginning of fall classes at Elkhorn North High School on August 16th.  The posted detour for this extended closure of 180th Street will utilize Blondo Street, 192nd Street, and Fort Street.
 
February 18, 2022
Earlier this week, the contractor began driving piling for the final bridge structure included in this project, carrying 180th Street over Whispering Ridge Creek between Locust and Emmet streets.  As we move into spring and warmer temperatures return, the contractor will continue work installing storm sewer and completing the paving of 180th Street and side street connections between Blondo Street and West Maple Road.  Watch for further updates on the schedule for planned work on the Maple intersection and further north.
 
August 31, 2021
As of 9:30 this morning, August 31, Phase 1 of the project is officially open to traffic, allowing travel along Blondo Street and 180th Street south of Blondo.  180th Street between Blondo Street and West Maple Road remains closed to traffic as the contractor continues Phase 2 work.  Please remain mindful of all posted signing, traffic signals, and construction traffic entering and leaving the site.
 
August 11, 2021
As the contractor puts the finishing touches on Phase 1 work on Blondo Street and 180th Street south of Blondo in preparation for opening those roadways to traffic in the coming weeks, project work will begin to move northward into Phase 2.  180th Street south of W Maple Road will be closed to traffic beginning Monday morning, August 16th.  Please remain mindful of all posted signing and be aware of construction traffic entering and leaving the site.
 
March 11, 2021
The contractor continues to make preparations to place concrete for the driving surfaces on the two viaducts that will carry 180th Street across Old Lincoln Highway, the Union Pacific Railroad tracks, and the West Papillion Creek.  They anticipate completing these bridges in the coming months, and with the onset of Spring will begin to work on preparations to pave the remainder of 180th Street and Blondo Street in Phase 1.  Progress remains on target to reopen Blondo Street and 180th Street between Blondo and W Dodge Road by late Summer 2021.  In the coming days, the contractor will begin work on a soil retention structure near Emmet Street, followed by construction of the new bridge that will carry 180th Street over Whispering Ridge Creek in this area.  Please remain mindful of all posted signing and be aware of construction traffic entering and leaving the site.
 
January 4, 2021
The contractor has placed all of the superstructure steel on the parallel viaducts that will carry 180th Street across Old Lincoln Highway, the West Papillion Creek, and the Union Pacific Railroad tracks and has begun to work on decking.  They have also completed the construction of the new structure that will carry Blondo Street over Whispering Ridge Creek, and are nearing completion of another structure near the western end of the project on Blondo.  Paving of 180th Street has been completed south of Old Lincoln Highway, and from Blondo to N HWS Cleveland.  Through the remainder of this winter, the contractor will continue to progress with decking of the viaducts and will focus on completion of the two box culverts that are part of the project.  In the coming weeks, work may begin on the second box culvert, which is just to the north of W Maple Road.  Progress remains on target for a late Summer 2021 reopening of Blondo Street and 180th Street south of Blondo.  Please continue to be observant of all posted signing and aware of construction traffic entering and leaving the site.
 
August 28, 2020
The contractor continues work on the structures that will carry 180th Street over West Papillion Creek, Old Lincoln Highway, and the Union Pacific Railroad, and anticipates setting beams this fall. They also continue to work on the structure that will carry Blondo over Whispering Ridge Creek, and continue to work on preparation to pave portions of 180th Street south of Old Lincoln Highway in the coming weeks. They will continue structure work through the remainder of the summer, fall, and coming winter, in anticipation of making pavement connections and remaining on schedule to reopen Blondo and 180th Street between Blondo and W. Dodge Road by late Summer 2021.
 
May 18, 2020
Please note: the previously scheduled closure to begin Monday, May 18th has been delayed. Beginning Thursday, May 21st, the contractor will close Blondo between 176th Avenue and 183rd Street to begin reconstruction of Blondo Street, the bridge crossing Whispering Ridge Creek, and a large box culvert. 180th Street will be closed south of N HWS Cleveland Boulevard at this time. This closure is anticipated to be in place until Fall 2021.
 
May 11, 2020
Beginning May 18th, the contractor will close Blondo between 176th Avenue and 183rd Street to begin reconstruction of Blondo Street, the bridge crossing Whispering Ridge Creek, and a large box culvert. 180th Street will be closed south of N HWS Cleveland Boulevard at this time. This closure is anticipated to be in place until Fall 2021.
 
Work continues on the viaducts between N HWS Cleveland Boulevard and Blondo Street, and the contractor will continue earthwork and storm sewer installation in preparation for paving of the new pavement section. Utility work will continue along 180th Street north of Blondo, and construction traffic will be active in the area throughout, so please continue to be mindful of that while traveling near this and other work zones.
 
March 20, 2020
  • The contractor has begun bridge construction and grading efforts for Phase 1, working along Blondo and in the area of Old Lincoln Highway.  Please continue to watch for construction traffic on 180th Street and Blondo Street.  Meanwhile, the contractor continues to work on tree clearing along the project.  Several large trees adjacent to the roadways will be removed next week, which will necessitate short term lane closures.
  • On Monday, March 23, the contractor will close 180th Street between Locust Street and Emmet Street for tree clearing.  This work will be completed on Monday, and 180th Street will be reopened by the evening rush.
  • March 24th through March 25th, the contractor will close 180th Street between West Maple Road and George Miller Parkway for tree clearing.  This work will be completed, and the roadway reopened, by the evening rush March 25th.
February 3, 2020
Beginning later this week, the contractor will begin clearing and tree removal along the project corridor. Work will begin south of Blondo and progress to the north.  Short term road closures and lane shifts can be expected during this time.  Watch for construction traffic.
The County has installed a construction camera. Please see below for the direct link to view the camera.

 

Project Resources:

 Contact Us

To provide your input about a specific location within the project area, visit the City Map.

 Queries

Ryan Ruff
Douglas County Engineer's Office
402-444-3289